Interrupt work on a task
If you need to interrupt work on a
task, you can split the task so that part of it starts later in the
schedule.
- On the View menu, click Gantt Chart.
- Click Split Task .
- On the task's
Gantt bar, click the area of the bar on the date where you want the
split to occur and drag the second part of the bar to the date that you want
work to begin again.
Printing in MS Project
You can now
change the number of the first printed page. For example, if your current
project has ten pages, and you only want to print pages 9 and 10, you can now
print them as pages 1 and 2.
-
On the
File menu, click Page Setup.
-
On the
Page tab, type the number you want in the First page number box.
If you wish to voice your opinion, or wish to be removed from our mailing list, please click
here. It is not our
intent to annoy anyone – We’re here to assist you in any way we can. Please let us know how we’re doing.
|